PROJECT DESCRIPTION :
Runway lighting system and monitoring automation were carried out in Kars Harakani Airport. Hitachi HX modular series PLC and SCADA are preferred in the project.
In project scope;
- Runway lighting and monitoring were performed on 5 pcs computers from 4 different locations.
- The system is designed in such a way that the user can easily detect various simulations via SCADA.
- There are two PLC configurations in the system. PLCs control a total of 38 CCRs (Constant Current Regulators). These two PLCs communicate with fiber optic communication network.
- 2 pcs. double-way runway control is provided.
- 38 CCR (Constant Current Ragulator) control and monitoring has been performed within automation with various aviation scenarios.
- Various operating scenarios are controlled by automatic authorization.
- At the user level, all movements, events and alarms for the past are taken as reports. Thus, all movements of the operator are recorded.
- Outside the runway, the apron, taxiway and lighting of various locations have been made to work automatically and manually.
- Foreign users are prevented from interfering in different user and authority levels.
- After all the processes have been completed, on-site testing and commissioning have been completed, the system has been delivered in a running condition.